10-4.
The type, amount, and timeliness of information passed from higher to lower headquarters directly impact the lower unit leader’s TLP. Figure 10-1 on page 10-2 illustrates the parallel sequences of the MDMP of a battalion with the TLP of a company and a platoon. The solid arrows depict when a higher headquarters’ planning event could start the TLP of a subordinate unit. However, events do not always occur in the order shown. For example, TLP may start with receipt of a warning order (WARNORD), or they may not start until the higher headquarters has completed the MDMP and issued an operation order (OPORD). WARNORDs from higher headquarters may arrive at any time during TLP. Leaders remain flexible. They adapt TLP to fit the situation rather than try to alter the situation to fit a preconceived idea of how events should flow.